Friday, May 29, 2015

29 May 2015

The access road through the cemetery as well as binder layer paving are complete.  Finishing touches continue inside.



















Friday, May 15, 2015

15 May 2015

Final touches are being completed on the interior of the building.  Also, final land development and preparations for paving are underway.














Saturday, May 2, 2015

2 May 2015

Exterior concrete work, multi-purpose hall HVAC, bathroom fixture, and kitchen cabinetry work occurred over the past week.










Friday, April 24, 2015

24 April 2015

Stone, tile, door, plumbing fixture, and kitchen install work are all ongoing...









Thursday, April 16, 2015

16 April 2015

Drop ceiling tile, kitchen flooring, bathroom flooring, bathroom wall tile, exterior stone, and sidewalk excavating are all ongoing this week.